MZ101
Timeline
Dec 2021
Jan 2022
February
March
April
May
MZ101 robustness testing plan
MZ101 application testing plan
Release MZ101-P1 drawings for
fabrication
Build MZ100-2 for testing critical
controls design changes
RT mobility application
study complete for JLG mobility
base requirements
Benchmark MZ101 cost
June
Resolve motor & gearbox
supply chain issues
High level manufacturing strategy
outline for new building setup
Primary function testing
and debug
Evaluate use cases of all current
ML150 accessories
July
Review FEA Results
Perform first full FEA of production
intent design release
Validate critical functions
of wireless handle w/ gripper
August
Perform second full FEA of production
intent design release
Electrical documentation complete
with all critical components for
manufacturing MZ101
Setup electric gripper testing
on ML150 for application,
debug, and robustness
Work with vendors to get forecast
and lead time understood for long
lead electronics.
Executable manufacturing plan
for setup in new building
Start ordering long lead electronics
to protect production supply
Marketing strategy outline
MZ101 official production forecast
for vendors to protect supply chain
September
Validate production intent
motor controls w/ temperature
compensation complete
Finalize complete software
validation plan
Marcus on leave
Marketing pictures and videos???
Working MZ101-P1A production
intent prototype
Prepare customer design review
application presentation
Customer facing spec sheet
GUI layout requirements
outlined
Working MZ101-P1B production
intent prototype
October
Production design release for 1st
manufacturing test run (Rev A)
Customer R&D design review
application meeting
Production software functions
locked down
Inhouse testing with real masons
MZ101-P2A design release?
(Parts or machine)
GUI requirements locked down
Risk assessment complete
Draft risk assessment complete
Start system software validation
and debug for production
Show unit / marketing requirements?
November
Executable marketing plan
MZ101-P2A working unit?
Pre-orders?
GUI complete
December
Draft CE assessment complete
Assembly documentation for
manufacturing floor builds
1st MZ101 pre-production unit assembled
and debugged
Software validated
Jan 2023
Final update and release of all
production drawings (Rev B)
Handoff to operations to
execute on manufacturing
Final setup of manufacturing line
CE certification plan complete
February
Operations owns MZ101
manufacturing efforts
World of Concrete
March
1st MZ101 production unit shipped