execom July 16

DRRM

SMS from PAGASA

Jul16-Jul20

billboards putting up completion

Jul16-Jul20

AWS installation in Capiz (Pontevedra)

OCD GIA

r

Bidding of equipment ongoingsix months ongoing, released December 2011

WVCIERD

project proposal for system in management of Tigum Aganan equipment

S&T scholarship

release of stipend for freshmen

encoding for active scholars is ongoing for immediate release of stipend

budget preparation

Jul16-Jul20r

for submission to congress

2013 budget

includes foreign travel

challenge is provision of personnel benefits

FAS

ARTA

standard compliance with PSTCs

flow chart and anti fixing and civil service hotline

Jul16-Jul31

OHS

OHS documentation

Jul16-Jul20r

establish documentation for OHS implementation

conduct regular earthquake drill

Jul16-Jul20r

issue SO for designation of safety officers

designation of safety officers

Jul16-Jul30r

teach PDRRMC on conducting preventive maintenance of equipment

BP 202

Jul16-Jul20

basis for determining budget allocation

2012 submission is for reference

2013 ISSF submitted

revise but incorporate all in one document

submit BP 202 for 14.5M GIA

prepare per program

community-based projects

support for research and development

support for local consortium

institutional support for technology resource centers

include GAD related projects

submit BP202 for all GIA project

prepare 2 versions

Jul16-Jul20

for locally funded, less than 1M

r

for local approval

for projects in excess of 1M

validate with PSTCs before submission

Jul16-Jul18

ManCom

Boracay trip is considered Q2 ManCom

Mar19 is Q1 sked

Q3 sked is