Detailed Scope Review

m

All Phases

Basis of Design

Key Assumptions

Planning Horizon - June 2024 - June 2074 (50 years)

Design life - 100 years

Throughput / fleet - updated container shipping fleet and design vessel forecasts will be provided to the Consultant within 10 Business Days

The Supply-Chain will need to accommodate an upper end forecast of 1.2million TEU p.a. in 2030 and 3.7million TEU p.a. in 2070.

The design should consider additional “buffer” capacity in each Stage of the Terminal Component development to ensure fluctuations in demand can accommodated without major disruption to operations due to infrastructure
constraints (‘resilience’).

Vessel size - Initial design vessel will be 14 000 TEU vessels (with scalability up to 18 000 TEU vessels during the next 50 years

Number of terminal
operators

The Consultant shall consider two operators as a starting point for the design work noting this is subject to change (transitional arrangements, automation/technology
and competition policy approaches may suggest alterative to status quo).

A concept design and footprint for Anketell Road from Leath Road to Tonkin Highway will be provided

Road freight

MRWA will provide the outputs of the road modelling and design processes at the relevant intervals to facilitate Consultant Supply-Chain modelling

Rail Frieght

Westport will provide a report on known inefficiencies and issues in network via the Baseline Constraints report.

o/d

The address of all container destination and origins, and address up to the top 25 trucking destinations (as of 2021 direct from port, or after loading from rail IMTs) and origins will be provided

LLOS

The (draft) LLOS report will also be provided to the Consultant on award which will include Westport agreed high level options and locations for future configurations of
road, rail, IMT/ECP/DC design (including infrastructure, operations, technology and governance) having been through an MCA, order of magnitude costing and rapid CBA.

Mode Share

A general direction for a rail share over 40% should be considered, but optimisation is expected to arrive at the ideal share

Phase 1 (Initiation)

Basis of Design

Stakeholder liaison

2x BoD Workshops

Provide an initial BoD within 30 days

Supply-Chain Integrated Design and Modelling

Gap Analysis

Supply-Chain Integrated Design

Develop interface processes with all models and the Supply-Chain Integrated System Model

Ensure all models provide the output data as required by the interrelated Westport projects

Ensure all design, drawings and documentation are aligned to the relevant output

Whole of Supply Chain Component

identify those potential measures that apply at a whole-of-Supply-Chain level to drive increased Supply-Chain System performance - feed into Long List of Options

Input to Decision Making Process

Actively engage with the Commercial and Economic Workstream and ensure that the Interface Management Plan addresses ongoing engagement

Prepare a decision-making process plan which details the interfaces between the Commercial and Economic Workstream project and this Project with respect to; timing, scope, quality, format, responsibilities etc

Work with the Economic Workstream project to agree input and output templates for the subsequent stages of The Project

Provide a brief strategy for Westport Stage 3 quantity surveying and costing identifying what approaches will be undertaken to minimise costs prior to Business Case consideration by Government

Ensure the costing strategy in alignment with Infrastructure Australia requirements and the expectations of private sector operators / investors (based on Consultants experience), or alternatives are approved by Westport;

Actively participate in a Base Case Parameter workshop (a concurrent project being delivered by Westport) to ensure outputs generated by the Consultant align to the Business Case project requirements

Review the Performance Targets (for each Performance Measure)

Validate the Base Case parameters with Westport’s Commercial and Economic workstream

Geotechnical and Enviro Studies

Desk Study Only

Gap Analysis

Spec Production

Costing

Delivery of asdditional surveys excluded and on approval by Westport

Deliverables

Phase 1

BoD

Gap Analysis Report

Incl. brief product scopes for all Deliverables for approval

Subtopic

Supply Chain Modelling

Visualisation Tool

c1

Fit-for-purpose visualisation tool to facilitate informed and timeline decision making processes

Show each short-listed Option (Phase Three) overlayed on an aerial view of the Perth-Peel region, including Staging over the planning period and identification of footprints over existing land uses that may require acquisition (e.g land required to facilitate expansion of an IMT);

Show agreed important metrics (or parameters) to visualise potential bottlenecks across the Supply-Chain over the planning period and other key supply chain wide information such as carbon emissions, total cost, environmental impact quantum etc.;

Show, on demand, a summary of information for each Component (for each short-listed Option)

Allow toggling of a limited number of key metrics (suggested by the Consultant and agreed by Westport) with a real-time response in the visual simulation to demonstrate the impacts on both container movement across the Supply-Chain and an agreed number of key metrics measures and costs (for each short-listed Option); and

Be suitable for viewing and use by informed but not expert audiences including Project Partners, relevant Ministers, and key stakeholders.

The tool will be able to be handed over and run by Westport office staff in the absence of the Consultant for the purposes of certain briefings.

The Consultant and Westport will jointly explore opportunities to enhance this user interface by linking it with Westport’s economic and environmental modelling to provide scenario and sensitivity analysis through a single dashboard.

Constraints Management Support

The Consultant shall make reasonable assumptions, based on previous relevant experience, on the constraints management scope of work, such as impact studies, engineering work, estimation work and quotations, that will be undertaken by the ‘constraint owners’ themselves e.g. Western Power, Telstra etc, or their consultants.

c1

Program

Provide initial BoD within 30 days

LLOS