My SMED projects at Avtec (by Rohit Kapote) - Operations and supply Chain management by Filipe Amado

Why did I choose this topic?

The Reason I choose this topic

I have gathered 6-months experience in working on these project

SMED was a topic taken up by experts in the operations industry, I was intern and people ridiculed me upon taking up such a hard project

I achieved high success

SMED is a important lean tool, and sharing my experience is valuable as I can club it with the session 7 on lean to understand further

About SMED

What Is SMED

How to imply SMED

Video

In this short video we learn that

We require SMED when changing from product A to product B on a machine this is called changeover

nowadays the costumers are demainding smaller batches and higher frequency meaning we have to minimise the waste in the process

SMED converted large changeover time of 4-6 hours to single minute exchanges!

There are 6 steps to make this happen:

Start with 5S

observe the process

Internal process

changes when the machine is not operating

External process

changes when the machine is running

Change internal to external - Reduce waste

Reduce the time of internal activities

Reduce the time of exertenal activity

Repeat 3-4 steps continuously

Examples of SMED

Industrial examples

In this video we the practical industrial application of how dies are being changed without the application of SMED and then with the application of SMED the amount of time reduced

Everyday example

This is a simple video of a father changing the diaper of his child, it is a simple understanding of what SMED is.

Best SMED practises in companies

Article on applying SMED in Turret punching machine-https://bit.ly/30ANXya

The Effect of SMED on Benefits Gained in Maquiladora Industry -https://bit.ly/38h62nw

Toyata and SMED -https://bit.ly/2TG7agn

Lean tools related to SMED

5S

What is 5S?

Everything has a place and a place for everything, this is a cleaning too to keep your work environment health and in order u

Everything has a place and a place for everything, this is a cleaning too to keep your work environment health and in order using these 5 s

Why is it important when applying SMED

SMED is a very complex process, and if we don't apply 5S principle everything will get messy.

Easier observation because of 5S

keeping the right mechanical tools sorted can help you with reducing the time.

Kaizen

What is kaizen?

The change for the good

The change for the good

Why is it important when applying SMED

Many firm need to meet the changing demand of the current world, therefore they need to change and thus Kaizen is used to change the production time in SMED

Many firms hold Kaizen meets to reduce SMED

Genchi Gembutsu

What is Genchi Genbutsu?

Subtopic

Subtopic

Why is it important when applying SMED

Onsite Inspection of every machine is important in SMED because:

inorder to reduce time employees reduce quality which is not desirable

Employee can be organised

The founder of SMED started the process with Genchi Genbutsu

About Avtec

Components made at AvTec

Subtopic

What sectors are Avtec in?

Powertrain

Powertrain

transmission components

precision-engineered products manufacturer

Avtec ltd

Part 6880090

A total of 140 parts made per month

The part is a brake flange

Engineering Drawing of Part 6880090

Engineering Drawing of Part 6880090

Analysis of the drawing

The drawing contains 8 holes with 4 operations on each hole

They used 4 tools for the 4 operations

The tools used for the holes were:

Slot Drill

Central Drilll

8.55mm Carbide Drill

Single tool

The Reason for using a Single Tool

The 3 tools had overlapping paths (overlapping was during change of the tools the tool went all the way down and came up to switch tools, the coming up was the redundancy) therefore combining the tools reduced tool path and therefore

Summary of the Result

Summary of the Result

The Result

Total machining time:13 mins! (Reduction by 15mins)

Time reduce/hole: 1,5mins

Flat bottom Drill

Time (total on the part & total on one hole)

Total Machining time: 28 mins

Total Machining time/hole: 3,30min

Observation of the VMC machine

Part 80001286

A total of 160 parts made per month

The part is a TT Transmission Housing

Drawing of Part 80001286

Drawing of Part 80001286

Analysis of the Instruction Sheet

Contains mainly turning operation

Roughing

Finishing

Tools used

Rough tool

Single tool with different inserts

Signature of tool signature was changed in order to increase the tool travel and remove the CNC redundant commands in order to do the turning operation in optimum time.

Summary of the Result

Summary of the Result

The result

Total machining time: 65 minutes per product

Reduction in time: 15 minutes per product

Finish tool

Time (total on the part)

Total Machining time: 80 minutes

Observation of the VTL machine

Part 150210880

A total of 180 parts made per month

The part is a CT100 Transmission Housing

Drawing of Part 1502100880

Drawing of Part 1502100880

Analysis of the Instruction Sheet

Operations involved

Milling

Boring

Drilling

Tools used

Finish Mill

Rough Mill

Milling Cutter

After failure of the bigger cutter, new cutter was introduced with different specifications. Usage of new cutter produced lesser noise and effective operation.

Summary of the result

Summary of the result

The Result

Total machining time: 63 minutes per product

Reduction in time: 12 minutes per products

Chamfering Tool

Time (Total on the part)

Total Machining time: 75 minutes

Observation of the VMC Machine

The Ending Note

Applying SMED in Avtec was not an easy project. the main challenges were

Understanding complex Engineering Designs

Standing and observing the machine for several hours everyday

Changing the CNC code

Future

SMED has a large scope at Avtec as Avtec is a old firm but facing a lot of new orders and demands. SMED is in the forefront to match them.

I see Lean tools as the major part of the smallest organisation simply because of its importance

Recommendation

Avtec cut time by several minute in SMED but due to their SMED incapability they could not be fully lean. I recommend to gather the resources to be leaner

Take aways

Difficult job to apply lean

must in every industry

The understanding of out the lectures help me see a lot of examples where companies have benifited from lean