Projet Migration Rise
Migration type
Brownfield
Lift & Shift
System Copy
Dev
Provide System Skeleton for S/4 installation on ECS
Provide Migration server
Prepare SWPM on Migration Server for temporay ASCS Installation
Execute preparation activities on source system
Perform Backup of source stystem
Transfer Backup file to SAP Rise
Move Backup on Hana Server
Execute SWPM on migration server to trigger S/4 Hana restore
Switch Migration server ASCS/PAS to SAP ECS ASCS/PAS
Execute post system copy on SAP ECS infrastructure
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request to start SAP Application Server on Rise)
Create Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Technical post-ops after SAP PAS switched on Rise
Functional post ops
S/4 DEV is live on Rise and ready to use
qual
Provide System Skeleton for S/4 installation on ECS
Provide Migration server
Prepare SWPM on Migration Server for temporay ASCS Installation
Execute preparation activities on source system
Perform Backup of source stystem
Transfer Backup file to SAP Rise
Move Backup on Hana Server
Execute SWPM on migration server to trigger S/4 Hana restore
Switch Migration server ASCS/PAS to SAP ECS ASCS/PAS
Execute post system copy on SAP ECS infrastructure
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request to start SAP Application Server on Rise)
Create Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Technical post-ops after SAP PAS switched on Rise
Functional post ops
S/4 DEV is live on Rise and ready to use
Prod
Provide System Skeleton for S/4 installation on ECS
Provide Migration server
Prepare SWPM on Migration Server for temporay ASCS Installation
Execute preparation activities on source system
Perform Backup of source stystem
Transfer Backup file to SAP Rise
Move Backup on Hana Server
Execute SWPM on migration server to trigger S/4 Hana restore
Switch Migration server ASCS/PAS to SAP ECS ASCS/PAS
Execute post system copy on SAP ECS infrastructure
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request to start SAP Application Server on Rise)
Create Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Technical post-ops after SAP PAS switched on Rise
Functional post ops
S/4 DEV is live on Rise and ready to use
Tenant Copy
DMO
Preparation
On Premise: Create copy of production system to SBX On Premise
SI checks (Simplification Items)
Note OSS Installation
Report Execution
On Premise systems: Install DMIS add-on for migration Cockpit
Install ATC system for Custom Code analysis
Install SAP NW AS ABAP System
7.52 ABAP on Any DB (Limited functionality but no additional licenses)
S/4 Hana
Note OSS Installation on source system (ECC)
Connect ATC to ECC system
Readiness Checks / HDB Sizing
Note OSS Installation
Report Execution
DEV System
Conversion
S/4 Conversion from ECC On Premise to S/4 Rise (DMO)
Source System(ECC On Prem)
SUM: Launch SUM
SPAU / SPDD Adjustments
SUM on source (end)
Transfert files to Target system
Rsync
sftp
azcopy (Azure specific)
Target System(S/4 Rise)
Install Temporary PAS on migration Server
SUM on migration Server (End of DMO)
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request to start SAP Application Server on Rise)
Create Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Technical post-ops after SAP PAS switched on Rise
Functional post ops
S/4 DEV is live on Rise and ready to use
Qual
Conversion
S/4 Conversion from ECC On Premise to S/4 Rise (DMO)
Source System(ECC On Prem)
SUM: Launch SUM
SPAU / SPDD Adjustments
SUM on source (end)
Transfert files to Target system
Rsync
sftp
azcopy (Azure specific)
Target System(S/4 Rise)
Install Temporary PAS on migration Server
SUM on migration Server (End of DMO)
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request to start SAP Application Server on Rise)
Create Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Technical post-ops after SAP PAS switched on Rise
Functional post ops
S/4 DEV is live on Rise and ready to use
Dry-Run
Conversion
S/4 Conversion from ECC On Premise to S/4 Rise (DMO)
Source System(ECC On Prem)
SUM: Launch SUM
SPAU / SPDD Adjustments
SUM on source (end)
Transfert files to Target system
Rsync
sftp
azcopy (Azure specific)
Target System(S/4 Rise)
Install Temporary PAS on migration Server
SUM on migration Server (End of DMO)
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request to start SAP Application Server on Rise)
Create Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Technical post-ops after SAP PAS switched on Rise
Functional post ops
S/4 DEV is live on Rise and ready to use
PROD System
Conversion
S/4 Conversion from ECC On Premise to S/4 Rise (DMO)
Source System(ECC On Prem)
SUM: Launch SUM
SPAU / SPDD Adjustments
SUM on source (end)
Transfert files to Target system
Rsync
sftp
azcopy (Azure specific)
Target System(S/4 Rise)
Install Temporary PAS on migration Server
SUM on migration Server (End of DMO)
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request to start SAP Application Server on Rise)
Create Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Technical post-ops after SAP PAS switched on Rise
Functional post ops
S/4 DEV is live on Rise and ready to use
Greenfield
Dev
System provisionned by SAP
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Post processing
Create new clients / Clients copy
language supplementation
Transport route configuration
Import ot Transport Orders using STMS (WARNING: For Mass Import there is no possibility to use OS scripts)
Data Migration (Migration Cockpit)
Qual
System provisionned by SAP
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Post processing
Create new clients / Clients copy
language supplementation
Transport route configuration
Import ot Transport Orders using STMS (WARNING: For Mass Import there is no possibility to use OS scripts)
Data Migration (Migration Cockpit)
Prod
System provisionned by SAP
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Post processing
Create new clients / Clients copy
language supplementation
Transport route configuration
Import ot Transport Orders using STMS (WARNING: For Mass Import there is no possibility to use OS scripts)
Data Migration (Migration Cockpit)
Bluefield
Preparation
On Premise: Create copy of production system to SBX On Premise
SI checks (Simplification Items)
Note OSS Installation
Report Execution
On Premise systems: Install DMIS add-on for migration Cockpit
Install ATC system for Custom Code analysis
Install SAP NW AS ABAP System
7.52 ABAP on Any DB (Limited functionality but no additional licenses)
S/4 Hana
Note OSS Installation on source system (ECC)
Connect ATC to ECC system
Readiness Checks / HDB Sizing
Note OSS Installation
Report Execution
DEV System
Conversion
S/4 Conversion from ECC On Premise to S/4 Rise (DMO)
Source System(ECC On Prem)
SUM: Launch SUM
SPAU / SPDD Adjustments
SUM on source (end)
Transfert files to Target system
Rsync
sftp
azcopy (Azure specific)
Target System(S/4 Rise)
Install Temporary PAS on migration Server
SUM on migration Server (End of DMO)
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request to start SAP Application Server on Rise)
Create Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Technical post-ops after SAP PAS switched on Rise
Functional post ops
S/4 DEV is live on Rise and ready to use
Qual
System copy from S/4 DEV
Create SAP Service Request for System Copy
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Post processing
Create new clients / Clients copy
language supplementation
Transport route configuration
Import ot Transport Orders using STMS (WARNING: For Mass Import there is no possibility to use OS scripts)
Data Migration (Migration Cockpit)
Preproduction
System copy from S/4 DEV
Create SAP Service Request for System Copy
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Post processing
Create new clients / Clients copy
language supplementation
Transport route configuration
Import ot Transport Orders using STMS (WARNING: For Mass Import there is no possibility to use OS scripts)
Data Migration (Migration Cockpit)
Dry-Run
Performance tests
Production
System copy from S/4 DEV
Create SAP Service Request for System Copy
SAP ECS Handover
Complete steps of Handover document (xls)
Create SAP Service Request for PCE Postproccessing
Create Service Request 10 days before requested date
Handover duration: 4 days for non Prod
Post processing
Create new clients / Clients copy
language supplementation
Transport route configuration
Import ot Transport Orders using STMS (WARNING: For Mass Import there is no possibility to use OS scripts)
Data Migration (Migration Cockpit)
Dry-Run
Performance tests
Data Migration using Migration Cockpit
Cutover preparation
Rise Infrastructure Set up
Network
Setup Connectivity from On Premise to Rise (VPN, MPLS...)
VNET Peering (Service Request)
DNS Replication
Autorize SAP Standard ports
Provide signed SSL certificates
System Provisionning
S/4 & Hana system provisionning
Migration server
Web Dispatcher
Cloud connector
other?
Landscape configuration
SAP Webdispatcher configuration
Fiori Activation
Load balancer configuration (Service Request)
Define ECS Load balancer url
Inbound interna
Inbound External
Deploy SSL Certificates
Allow Outgoing traffic from S/4 to Internet
SSO Configuration
SAPGUI
Kerberos using Secure Login Client(without Secure Login Server)
Using Sercure Login Services (BTP Service, additional costs)
FIORI
SSO with Cloud Identity Services
With Secure Login Services (on BTP)
SAML2 SSO using customer corporate AD(eg: Entra)
Mount shares on servers (CIFS, NFS..)
Cloud Connector
Deploy UI SSL Certificate
Deploy server SSL certificate
Connect to BTP Subaccount / Backend system (if identified scenarios)
Reginfo configuration (whitelist remote systems to connect to SAP)
Update / Check SAPGUI version with S/4 supported version on customer side
S/4 ABAP Configuration
Configure Operation Mode with Workprocess distribution
Set profile parameters (RZ10)
Schedule Technical jobs
Configure Logon Groups
BTP / CALM
Cloud ALM
Provisionning
Connect Managed systems
BTP
Configure BTP services
Adobe Forms service
Prepare to Run
Set up Monitoring
SAP Monitoring
Hana Monitoring
ITSM ticket on SAP mail alert
Cyberwatch for SAP
Retyna
Backup / Restore test (Validation)
SAP CQC Service
Schedule CQC Service
CQC Report Analysis
Apply SAP CQC Recommandations
DRP
DRP Configuration (SAP)
On Premise
Windows Admin Console
Install & configure Hana Studio
Web Browser
SAP Web dispatcher Admin interface
Cloud Connector interface
Fiori Access
Job Scheduling
Remote server for job Scheduling (eg: VTOM)
Connect On Premise Systems to Rise
BW
Greenfield of Bluefield approach
DMIS Addon installation on ECC system for data migration (SLT)
Project Preparation
Architecture Review
On Prem Production performance analysis
Rise Landscape sizing review
Finops: Propose optimizations on architecture
Refreshs; Use of DSM (Data Sync Manager) instead of classical system copy
SLT: If greenfield or bluefield Project, check compatibility between DMIS Addon on On Premise system and S/4 version on Rise
DNS: Define DNS integration scnenario
DAT: Create inventory of all Rise servers with tecnical details (Technical Architecture Document)
CUTOVER: Define Technical conversion scenario for Production according to downtime window duration provided by customer
Backup: Check Rise Backup Policy meets customer requirements
BTP Onboarding: Onbarding customer to SAP Rise / BTP (presentation of SAP BTP functionalities and oXya service offer)
Outgoing Network traffic to internet: List outgoing connections from SAP to Internet
Interfaces: List interfaces with S/4
BTP: Are there Identified BTP services that will be used on Rise(eg: Adobe Form Services, Integration Suite, DRC...)?
Connectivity: Setup connectivity between On Prem and Rise Servers and authorize SAP standard ports
Pre-Requisites
SAP S-USER
SAP Handover document(xls) for all systems with credentials
Migration server login informations
Technical Assessment document(if available)
Project Management
Weekly sync up calls SAP
Rise Administration(Run Phase)
Create SAP Service Requests
Create Cases