TOD Projects Monitoring
(W4 Jan 2025)
TOD Dukuh Atas
Penataan Kawasan Karet
Tahap 1A - Akses St. Karet & Kanopi
(KCI)
Ijin : On Progress
Target : Feb 2025
Rekomtek/Surat Dukungan DSDA
Desain : Done
Dana : done (PT KCI)
Fisik : Not Yet Started
Target : Maret 2025
Tahap 1B - Promenade St. Karet-BNI City
(ITJ)
Ijin : On Progress
Target :
Rekomtek DSDA
Rekomtek DPHK
Desain : On Progres
Target :
Dana : done (Kontribusi PT MAS)
Rapim ?
Fisik : Not Yet Started
Target :
Tahap 2 - Penataan Simpang St. Karet
(ITJ)
Ijin : done
Desain : done
Dana : done (Kontribusi PT MAS)
Fisik : Not Yet Started
Pedestrianisasi Jl Blora-Kendal
BAPT : Pending tanda tangan Kadis DBM
Target :
BAPF : done
BAST : Pending BAPT DBM
Pelebaran Jl Pati-Juana
BAPT : done
BAPF : done
BAST : Pending BAPT DBM untuk Blora
Penataan Taman Kudus
BAPT : done
BAPF : done
BAST : Pending BAPT DBM untuk Blora
Peresmian
Gedung TH
Hotel
Fisik
Lantai 11 - 12 :
Target : W1 Feb 2025
Lantai 9 - 10 :
Target :
Gym
Beroperasi
Foodcourt
realisasi tenant :
TOD Bundaran HI
Kepgub : done
No.703/2024
Tanggal 4 Oktober 2024
Dana : -
Kajian : done
Skematik & FS
DED : -
PKS ITJ x WNI
Target :
Surat MRT No.1123/BOD-PD/PB.04
Tanggal : 11 November 2024
Ijin : -
IMB Persiapan