Subcontract

No

Subtopic

Is Remove and replace a 'Variation'

Yes

$13m

Time related costs

$2.5m EOT costs & Extension of Time

$750k Financing costs

Main topic

Main topic

Yes

$76m

Secure Variations-$9.65m

Unsecured Variations- $400k

Subtopic

$85

Delay, Disruption & Variations costs

Remove & Replace Direct costs

$5.7m

Consequential costs

$11M

NO

Insurance

Under 18.3 Subcontractors sole remedy is EOT

EOT for ' Water Damage' only

$5.7m

Disruption and Variations

$1.2m

Does decision to Deviate/ Accelerate constitute a Deviation Direction