Giza Palace Hotel and Spa (GPHS)
Site Preparation
Engineering Design
& Approval
Procurement
construction
Phase 1
Phase 2
Building 5
Struct. Works
Soil Replacement below SOG
Concrete
Sub Structure Works
Foundation
SOG 200 mm
Basement 2
Basement 1
Masonry Under SOG
Sub Structure Water Proofing
Arch. Works
Unit Masonry Assemblies
Basement 3
Basement 2
Basement 1
Cement Plaster
Internal Cement Plaster
Basement 1
Basement 3
Basement 2
External Cement Plaster
Remaining of Building 7
Struct. Works
Soil Replacement Under SOG
Concrete
Super Structure Works
4th Floor
5th Floor
Roof Floor
Domes
Masonry Under SOG
Sub Structure Water Proofing
Arch. Works
Unit Masonry Assemblies
3rd floor
4th floor
5th floor
Cement Plaster
Internal Cement Plaster
3rd floor
4th floor
5th floor
External Cement Plaster
Remaining of Building 8
Struct. Works
Soil Replacement Under SOG
Concrete
Super Structure Works
4th Floor
5th Floor
Roof Floor
Domes
Masonry Under SOG
Sub Structure Water Proofing
Arch. Works
Unit Masonry Assemblies
3rd floor
4th floor
5th floor
Cement Plaster
Internal Cement Plaster
4th floor
3rd floor
5th floor
External Cement Plaster
Steel Link
Erection and Installing
Arch. Works
Unit Masonry Assemblies
Cement Plaster
Internal Cement Plaster
External Cement Plaster
Building 12 till 3rd ground floor
Struct. Works
Soil Replacement below SOG
Concrete
Sub Structure Works
Foundation
SOG 200 mm
Basement 2
Basement 1
Super Structure Works
Ground Floor
Masonry Under SOG
Sub Structure Water Proofing
Arch. Works
Unit Masonry Assemblies
Basement 3
Basement 2
Basement 1
Cement Plaster
Internal Cement Plaster
Basement 3
Basement 2
Basement 1
External Cement Plaster
Building 13
Struct. Works
Soil Replacement below SOG
Concrete
Sub Structure Works
Foundation
SOG 200 mm
Basement 2
Basement 1
Super Structure Works
Ground Floor
Masonry Under SOG
Sub Structure Water Proofing
Arch. Works
Unit Masonry Assemblies
Basement 3
Basement 2
Basement 1
Cement Plaster
Internal Cement Plaster
Basement 3
Basement 2
Basement 1
External Cement Plaster
Phase 3