План организации — дерево

The process involves creating a website through a structured development approach. Initially, it focuses on front-end development, which includes writing source code, designing navigation structures and layouts, creating pages, and adding interactive features like user events calendars.

План организации — дерево

WEB Cab Edu

5. Delivery

5.3 Final report
5.3.4 Transfer to the customer all Project documentation
5.3.3 Write a report
5.3.2 Prepare all documents for the “closing” phase
5.3.1 Make a Project Closure Checklist
5.2 Support & Maintenance
5.2.1 Bug fixing (during 3 months)
5.1 Launch the website
5.1.1 SEO for the website

4. Testing

4.1 Testing
4.1.9 Write summary report
4.1.8 Write recommendations for improving product quality
4.1.7 Create a bug report for developers
4.1.6 Analyze test results
4.1.5 Assign user roles&train client on CMS
4.1.4 Manual QA
4.1.3 Multiple screen tests
4.1.2 Cross-browser compatibility
4.1.1 Website speed

3. Development

3.1 Create the website
3.1.4 Approve final result with the customer

3.1.4.1 Proofread & edit where required

3.1.3 Сontent writing and assembly

3.1.3.2 Receive content from the customer and add to pages

3.1.3.2.1 Add links&functionality to content

3.1.3.1 Set up CMS

3.1.2 Front-end development

3.1.2.1 Write front-end source code

3.1.2.1.3 Make navigating structure and site layout without the web content

3.1.2.1.2 Add special features and interactivity

3.1.2.1.2.1 User events calendar

3.1.2.1.1 Create pages

3.1.1 Back-End development

3.1.1.2 Write back-end source code

3.1.1.1 Connect to the server

2. Design

2.2 Approve the design
2.1 Create mockups
2.1.2 Design

2.1.2.4 Make final design final & visual assets

2.1.2.3 Design main pages based on approved home page

2.1.2.2 Identify colors & font

2.1.2.1 Review customer brand standards

2.1.1 Wireframes

2.1.1.2 Lay out home&main pages using a responsive grid

2.1.1.1 Establish a visual hierarсhy & placement of content

1. PM

1.4 Project Plan
1.4.8 Approve SW with the customer
1.4.7 Write the Statement of Work
1.4.6 Describe the external and internal functions of the project
1.4.6 Write a plan for working with stakeholders
1.4.5 Write a risk plan
1.4.4 Fill Gantt Chart
1.4.3 Draw up a project implementation schedule
1.4.2 Identify the processes of interaction and communication
1.4.1 Define roles, responsibilities and resources
1.3 WBS
1.3.2 Make WBS diagram
1.3.1 Create a list of project works
1.2 Project charter
1.2.4 Receive confirmation from the customer
1.2.3 Define the list of stakeholders
1.2.2 Estimate budget
1.2.1 Creating the basic version
1.1 Business case
1.3 Creating the final version
1.2 Creating the basic version
1.1.1.Conduct a briefing

1.1.1.1 Make questions to the customer