Work Breakdown Structure

Project Initiation

Define Project Scope

Create Project Plan

Obtain Necessary Approvals

Customer Review (John and Joan Smith)

Project Planning

Review Blueprints

Plan and Design the Layout

Obtain Building Permits

Milestone: Permits Approved (2023 March 5)

Project Execution

Foundation Construction

Site Preparation

Pour Foundation

Milestone: Foundation Poured (March 14)

Framing and Structure

Framing

Sheathing

Plumbing Installation

Electrical Installation

Mechanical Installation

Milestone: Dry-In and Inspections Passed (May 25)

Interior and Exterior Finishing

Wall Insulation (R-21)

Ceiling Insulation (R-38)

Floor Insulation (R-25)

Windows and Doors (NFRC Class 40)

Garage Construction (2 cars + 20-foot Winnebago)

Kitchen Appliances Installation

High-Efficiency Gas Furnace Installation

Milestone: Final Inspection (June 7)

Project Monitoring and Controlling

Foundation Inspection

Inspections (Plumbing, Electrical, Mechanical)
- May 25

Interior and Exterior Inspection

Seismic Stability Checks

Project Closing

Customer Handover

Final Walkthrough with Customers (June 7)

Customer Acceptance

Project Documentation