Categorías: Todo - insurance - costs - delay - disruption

por Edward O Reilly hace 12 años

304

EOR 1

The document discusses various financial implications and procedural considerations related to a construction project. Key issues include costs associated with delays, disruptions, and variations in the project scope, with particular emphasis on water damage.

EOR 1

Does decision to Deviate/ Accelerate constitute a Deviation Direction

Disruption and Variations

$1.2m

EOT for ' Water Damage' only

Under 18.3 Subcontractors sole remedy is EOT

Insurance

NO

Remove & Replace Direct costs

$11M

Consequential costs

$5.7m

Delay, Disruption & Variations costs

$76m

$85

Unsecured Variations- $400k

Secure Variations-$9.65m

Subcontract

Main topic

$750k Financing costs

$2.5m EOT costs & Extension of Time

Time related costs

$13m

Yes

Is Remove and replace a 'Variation'

No

Subtopic