Kategorier: Alle - assessment - testing - design - manufacturing

af Bill Martz 2 år siden

79

MZ101Timeline Draft

Efforts are ongoing to resolve supply chain issues related to motors and gearboxes while also focusing on primary function testing and debugging. A high-level manufacturing strategy for a new building setup is being formulated alongside evaluating the use cases of current accessories.

MZ101Timeline Draft

MZ101 Timeline

1st MZ101 production unit shipped
World of Concrete
Operations owns MZ101 manufacturing efforts

Jan 2023

CE certification plan complete
Final setup of manufacturing line
Handoff to operations to execute on manufacturing
Final update and release of all production drawings (Rev B)

December

Software validated
1st MZ101 pre-production unit assembled and debugged
Assembly documentation for manufacturing floor builds
Draft CE assessment complete

November

GUI complete
Pre-orders?
MZ101-P2A working unit?

Only necessary if there is a major learning from P1 build.


FEA and testing have shown no major issues, even at 30 degrees we still have almost a 5x factor of safety as a foreseeable misuse case.

Executable marketing plan

October

Show unit / marketing requirements?
Start system software validation and debug for production
Draft risk assessment complete
Risk assessment complete
GUI requirements locked down
MZ101-P2A design release? (Parts or machine)
Inhouse testing with real masons
Production software functions locked down
Customer R&D design review application meeting
Production design release for 1st manufacturing test run (Rev A)

September

Working MZ101-P1B production intent prototype
GUI layout requirements outlined
Customer facing spec sheet
Prepare customer design review application presentation
Working MZ101-P1A production intent prototype
Marketing pictures and videos???
Marcus on leave
Finalize complete software validation plan
Validate production intent motor controls w/ temperature compensation complete

4/28:

August

MZ101 official production forecast for vendors to protect supply chain

4/15

4/28

Marketing strategy outline
Start ordering long lead electronics to protect production supply
Executable manufacturing plan for setup in new building
Work with vendors to get forecast and lead time understood for long lead electronics.
Setup electric gripper testing on ML150 for application, debug, and robustness
Electrical documentation complete with all critical components for manufacturing MZ101
Perform second full FEA of production intent design release

July

Validate critical functions of wireless handle w/ gripper
Perform first full FEA of production intent design release
Review FEA Results

June

Evaluate use cases of all current ML150 accessories
Primary function testing and debug
High level manufacturing strategy outline for new building setup
Resolve motor & gearbox supply chain issues

May

Benchmark MZ101 cost
RT mobility application study complete for JLG mobility base requirements
Build MZ100-2 for testing critical controls design changes
Release MZ101-P1 drawings for fabrication
MZ101 application testing plan
MZ101 robustness testing plan

April

Dave L drastic hours cutback? - Jake full time to resolve
Interior mobility application study complete for JLG mobility base requirements
Resolve battery and power issues in cold weather

4/28

MZ101 Production intent prototype weldments release for quoting

March

Resolve Fort Robotics issue
Resolve overturning moment issues with MZ100
Design MZ101

February

Re-evaluate requirements and design of MZ100
Resolve temperature and motor feel issue
Perform initial application study

Jan 2022

MZ100 design release

Dec 2021

Initial controls feel signoff
Handle wireless resolved