Categorie: Tutti - challenges - success - design - communication

da Katherine Adams mancano 9 anni

200

East Bay plan

The project under discussion involves a design/build effort with a clear focus on audiovisual elements, with Odyssey selected for media development. Key initial steps include establishing a comprehensive project plan and communicating essential details.

East Bay plan

Production Process

Close-out

Transfer all exhibit items to the client and begin the warranty period. Archive paperwork essential to future warranty work and complete all financial deliverables.

Internal Close-out
Archive project documentation
Archive graphics
Close project in Epicor
Financial closeout
External Close-out
Warranty
Write thank you notes
Complete Manual
Final client review and approval

Production and Installation

Produce exhibit elements using client-approved drawings and samples. Ensure that all exhibits and functional and clean once installed.

Client Review
Punch list
Training
Installation
Clean
Test and touch-up
Install exhibit elements
Install structures
Sit preparation and unload
Pack and ship
Create On-site safety plan and installation manual
Trial Assembly
Revisions
In shop review
Add graphics
Production
Art

Murals

Sculpture

Fabrication

Interactives

Metalwork

Carpentry

AV
Graphics

Pre-Production

Clarify any unknowns, establish work goals, and define measures of success.

shop drawings should already be done and approved so this phase is truncated.

Verify availability of materials and order long lead items
Create QC
Review schedule
Revise work orders
Complete take-offs and draft exhibits

Design or Pre-Production

Final Design 100%

contract AV Media

Revise development schedule

create graphic files

Finalize all exhibit elements

Review

Submittals to clients and designers

Internal redline

Revise itemized cost plan

Create Shop Drawings

Produce mock-ups, prototypes, and samples

Organize graphic requirements and confirm scope

Produce samples

Prepare graphics and produce samples

Meeting
Project expectations
Design Development 80%

Revise detailed schedule

Present concept plan

Refine media proposal

Draft exhibit text

Design individual exhibits

Modify graphic styling

Refine concept sketches

Review means and methods

Itemize budget cost plan

Create AV media and Integration Spec and budget

Design Development 50%

Revise Schedule

Outline media proposals

List of image and object resources

Sample exhibit text

Outline of written concepts

Budget

Pre Design - Concept Development
Define Project Resources

Communication expectations

Project team roles and responsibilities

Deliverables

Mark Elliot will be the lead designer for WOED with PAtty as the content developer

John match deliverables in the RFP to these phases for review

Media approach

Existing collections and research

Themes and topics

Research sources

Stakeholders

Key messages

Target audience

Outcomes

Aims and objectives

Kick Off

Communicate key information and establish project plan.

Licensing
State contractor license

We are licensed in the state of California, confirm license number and make sure it is posted at jobsite.

State Business License is complete
Other
State Worker's Comp
Insurance
Accounting
County Tax
City Tax
State Income Tax
Consumer - Use Tax
Retail-Sales Tax
Credit Terms Net 30
Billing Format

contract says:

Contractor as set forth in the rate schedule documented in Exhibit B attached hereto and made a part hereof. All expenses incurred as part of this Agreement will be reimbursed at actual cost. Such compensation shall be full payment to Contractor (including expenses) for performance of said services; provided, however, that in no event shall the sum of total compensation paid Contractor and reimbursable expense exceed $ _______________without prior written authorization by District.

Contractor shall submit invoices for his/her compensable hours/work product and reimbursable expenses monthly, and District shall make payments on the approved reimbursable expenses within 30 days, provided that in no event shall the amount paid Contractor exceed that percentage of the maximum total compensation and expenses payable under this Agreement ($____________ ) which percentage equals the percentage of Contractor's work complete at the time.

I am negotiating and clarifying this requirement

Billing Timing

billing is progress billing monthly.

Prevailing Wage

9. Labor Code/Prevailing Wages

To the extent applicable, Contractor and Contractor’s subcontractors shall comply with the requirements of the California Labor Code including but not limited to hours of labor, nondiscrimination, payroll records, apprentices, workers’ compensation and payment of prevailing wages as determined by the Director of California Department of Industrial Relations. Contractor shall post a copy of the prevailing rate of per diem wages at each job site. Contractor shall forfeit fifty dollars ($50.00) for each calendar day or portion thereof for each worker paid less than the stipulated prevailing rates for any public work done under the Agreement by it or any subcontractor. Contractor shall defend, indemnify and hold harmless the District for any costs, claims and expenses arising from the failure of Contractor or Contractor’s subcontractors to pay applicable prevailing wage rates.

Administrative
Project Summary

Schedule

build gantt chart

QC plan

Julie to oversee design phase

Grant to oversee production phase

Measures of sucess

1. This project wil be a success if the costs are contained to the costs identified in the budget wiht a GPM of 30 on fab and install and 10-15 on design.

2. Client is very happy at the team effort at the end of the project and believes the visitor experience is a success.

3. project is done on time with no added costs to rush to the finish line.

* There are 6 interpretive Centers in this Park system and it could lead to new work.

Challenges

Design budget is modest and we have limited resources to participate in the design process and should focus on the fabrication. This will be a good challenges to confirm that WOED can work independantly.

Timeline is tight, and this I believe is the first time they have outsourced their work, so they may need some help staying on schedule.

Key deliverables

Subtopic

Scope of work

Project is a design/build with WOED. see proposal for budget and inital schedule.

Read RFP fro details on goals and interpretive requirements.

As AV is developed we have selected Odyssey to do the media, and Steve attended the interview

AV integration we will likely prep in house and install with our own forces. We may want to consider having Phil provide a portion of install and then be available for installation.

review Addendum Q&A

Budget review
Roll job in epicor