WBS
Retail Interior Design Website
6. Release
6.1. Website (the link to the website)
6.1.1. deploy the website
6.1.1.2. arrange the work of Customer Service
6.1.1.1. implement and launch the hosting
5. Testing
5.1. Testing Report (the document is on Google Drive)
5.1.8. approve the project rediness verification
5.1.7. run the Final Testing
5.1.6. correct the defects
5.1.5. make recommendations for the quality improvement
5.1.4. make the report of defects for the Development Team
5.1.3. analyse the the results
5.1.2. run the Testing
5.1.1. make a plan of the testing
5.1.1.2.estimate the risks
5.1.1.1. check the project requirements
4. Development
4.1. Graphical page templates (the link to the templates)
4.1.6. develop special feature coding
4.1.6.3. make visual interior constructor
4.1.6.2. make flash
4.1.6.1. make widgets
4.1.5. develop navigation
4.1.4. make graphical asset placement
4.1.4.2. make template structure/coding
4.1.4.1. make graphical splitting and optimisation
4.1.3. develop the server set-up
4.1.2. develop the structure of the pages
4.1.1. analyse the concept of the website
3. Design & Analysis
3.1. Clickable Prototype (the link to the clickable prototype)
3.2.3. approve the Clickable Prototype
3.2.2. make a Clickable Prototype
3.2.1. make up a website design concept
3.1.1. do the Project Kickoff
3.1.1.2. analyse the information and requirements
3.1.1.1. establish common goals and requirements
2. Recruitment
2.1 Development Team (full-time contracts)
2.1.7 onboard the new hires
2.1.6. offer a job and hire
2.1.5. interview the candidates
2.1.4. screen and make a short list
2.1.3. search for talents
2.1.2. plan the recruitment
2.1.1. identify the hiring need
1. Project Management
1.5. Final Report (link to the document)
1.5.1. make the Final Report
1.4. Status Report (link to the document)
1.4.1. make the status report schedule
1.3.Project Plan (link to the approved document)
1.3.4. approve the project plan
1.3.3. prepare Project Plan
1.3.3.2. assess the risks
1.3.3.1. estimate the cost
1.3.2. make WBS Outline
1.3.2.2. make the Network Diagram
1.3.2.1. estimate the cost (effort & duration)
1.3.1. make WBS
1.3.1.1. make the type of works list
1.2. Project Charter (link to the approved document)
1.2.2. project charter approval
1.2.1. set the goal, objectives and scope of the project
1.1. Business Case (link to the approved document)
1.1.1. gather the requirements